Explainer
P50 and P90 generation estimates
P50 and P90 are exceedance levels drawn from a modelled distribution of a project's energy production.
P50 and P90 are exceedance levels drawn from a modelled distribution of a project’s energy production. Under the stated model and period, P50 is the energy level with a 50 percent probability of being met or exceeded, and P90 has a 90 percent probability of being met or exceeded. For the same distribution and time basis, P90 is lower than or equal to P50. They are conditional model outputs. They are not guarantees, and they are not confidence intervals.
The distribution comes from an assessment rather than an observation. A wind energy assessment begins with site measurements, long-term reference data, flow and wake modelling, turbine power curves and layout, and gross-to-net loss estimates. It then quantifies uncertainty from measurement, long-term adjustment, spatial extrapolation, model performance, power curves, wakes, availability, electrical losses, environmental effects and curtailment. Combining those uncertainties with their assumed distributions and correlations produces the exceedance values.
The naming convention runs opposite to percentile convention and this is where readers go wrong. P90 is the 10th percentile when production is plotted from low to high. The number is high because the probability of exceeding it is high, not because the production is. Stating the direction explicitly avoids an error that reverses the meaning.
The time horizon is part of the definition and is frequently omitted. A one-year P90 addresses the variability and uncertainty of a single future year. A ten-year average P90 addresses the average across that period and sits closer to the central estimate, because some interannual variability averages out over a longer window. First-year, long-term mean, debt-tenor average and lifetime values cannot be substituted for one another, and a figure quoted without its horizon is not usable.
P50 is the median, which is not always the mean. When the modelled distribution is skewed the two separate, and using one where a financial model expects the other introduces a bias in a direction that depends on the skew.
These figures exist because they are used to size debt. A lender concerned with coverage in a poor year works from a lower exceedance level than an equity investor working from a central case, which is why the same project is described by several numbers at once. Each is correct for its purpose.
Two properties of the estimate limit what it can support.
The uncertainty estimate is itself modelled. The exceedance spread reflects assumed distributions and assumed correlations among uncertainty components. A narrower P50-to-P90 gap can mean a better-characterised site or a more confident set of assumptions, and the number alone does not distinguish them.
An exceedance level is not a performance guarantee. It describes a distribution conditional on the model being right about the site, the equipment, the losses and the operating environment. A systematic error in any of those shifts the whole distribution rather than showing up as a bad draw from it.
Asked on the floor
- Is P90 a worst case?
- No. It is the level with a 90 percent probability of being met or exceeded under the stated model. Outcomes below it are expected roughly one year in ten.
- Why is P90 called that when it is the 10th percentile?
- Because the convention is exceedance rather than percentile. Plotted low to high, P90 sits at the 10th percentile. Stating the direction avoids the most common error with these numbers.
- Can I compare two projects' P90 figures?
- Only if the time horizon matches. A one-year P90 and a ten-year average P90 answer different questions, and the multi-year figure is usually closer to the central estimate because some interannual variability averages out.
- Is P50 the average?
- It is the median of the modelled distribution. When the distribution is skewed it is not the arithmetic mean, and the two should not be substituted.
Sources
- National Renewable Energy Laboratory — Wind Plant Preconstruction: Energy Estimates and Losses (NREL/TP-5000-64735, May 2016)
- National Renewable Energy Laboratory — System Advisor Model Help (December 2021)
- International Electrotechnical Commission — IEC 61400-15-1:2025 Site suitability input conditions for wind power plants