Explainer
How horizontal is a horizontal well?
A horizontal well is a directionally drilled well with a high-inclination lateral section intended to run broadly along a target formation.
A horizontal well is a directionally drilled well with a high-inclination lateral section intended to run broadly along a target formation. “Horizontal” describes what the well is for rather than its geometry: the lateral need not be level, and it usually is not. It follows the formation, and formations dip, thin and vary.
The trajectory has three parts. The well begins vertical or near-vertical, builds angle through a curved section, and then continues laterally in or near the target. The Canada Energy Regulator describes the bit being steered sideways after the vertical section. Each part is drilled with different equipment settings and each contributes to the total length.
The purpose is contact. A vertical penetration crosses a thin or low-permeability reservoir once. A lateral runs along it, exposing far more wellbore to the rock that holds the hydrocarbons. In formations where the rock will not deliver fluid to a single point at commercial rates, this is what makes the well viable.
Measured depth and true vertical depth are different numbers, and confusing them is the most common error in reading well data. Measured depth follows the path of the hole through the vertical section, the curve and the lateral. True vertical depth measures straight down from surface. A well with a long lateral can have a measured depth several times its vertical depth, and pressure, temperature and geology all relate to the vertical figure rather than the measured one.
Drilling and stimulation are separate operations. In tight formations a horizontal well is usually paired with multistage hydraulic fracturing, and the pairing is so routine that the two get treated as one activity. The Canada Energy Regulator’s glossary preserves the distinction: drilling creates the borehole trajectory, fracturing stimulates the surrounding rock, and tight-oil reservoirs typically require the combination. A horizontal well in a permeable formation may need no stimulation at all.
Completion of the lateral is a further choice. It may be left open hole, lined, or cased and cemented and then completed through selected intervals. That decision governs how a stimulation treatment can be placed and how the well can be worked over later.
Two things published about horizontal wells are frequently over-read.
Regional design figures are not design rules. The BC Energy Regulator reports that most wells targeting the Montney in British Columbia are directionally drilled and explains the measured-depth and true-vertical-depth distinction, with example dimensions describing that population at the time of publication. Design differs by geology and operator, and a typical figure is not a specification.
Lateral length is not productivity. Longer laterals contact more rock and also encounter more variation in it, and completion design, rock quality and stimulation determine what the contacted rock delivers. Normalising production by lateral length changes a comparison without removing geological selection.
Asked on the floor
- Is the lateral actually level?
- Not necessarily, and it does not need to be. The lateral is steered to follow the target formation, which dips and varies. Horizontal is an operational description rather than a geometric guarantee.
- Why is measured depth larger than vertical depth?
- Because measured depth follows the path of the hole, including the curve and the lateral, while true vertical depth measures straight down. A long lateral makes the two diverge sharply.
- Is horizontal drilling the same as fracking?
- No. Drilling creates the borehole trajectory; fracturing stimulates the surrounding rock afterwards. The Canada Energy Regulator distinguishes them expressly, and tight reservoirs typically need both.
- Is the lateral left as open hole?
- It can be. The lateral may be left open, lined, or cased and cemented and then completed through selected intervals, depending on the formation and the completion plan.