Export licence, nameplate, contract, cargo: four different quantities

Four quantities in the LNG business are routinely reported as though they were one, and they measure different things at different points in a project's life.

Four quantities in the LNG business are routinely reported as though they were one, and they measure different things at different points in a project’s life. An export licence authorises a volume. Nameplate capacity describes a design. A sale and purchase agreement commits an annual quantity. Cargoes are what shipped. Each is real, none implies the others, and the gaps between them are where most claims about Canadian LNG go wrong.

The licence comes first chronologically and is the weakest evidence of activity. Export authorisation under the Canadian Energy Regulator Act requires evidence about the export source, volume, Canadian supply and demand, and market implications, and it grants authority up to stated quantities and conditions. It does not prove construction, secure feed gas, guarantee buyer performance, or establish that a single cargo will leave. It is permission, and permission expires unused.

Nameplate capacity is an engineering figure attached to a plant that may or may not exist yet. A liquefaction train treats and cools natural gas to a cryogenic liquid, with pretreatment removing water, acid gases, mercury and heavy hydrocarbons that would freeze, corrode or violate specification, followed by refrigeration cycles that remove sensible and latent heat. The output that results depends on the selected process, feed conditions, ambient temperature, driver, power source and integration. A rating is a design point, and warm weather alone moves actual output away from it.

Contracted annual quantity is a commercial commitment and comes from a different document again. A sale and purchase agreement sets term, annual and cargo quantities, scheduling, quality, price, delivery point, title and risk, shipping responsibility, remedies, force majeure, credit support, diversion and resale rights, measurement and dispute resolution. Take-or-pay language can require a buyer to take and pay or compensate the seller, alongside parallel seller obligations and contractual excuses. A publicly filed agreement illustrates possible terms rather than establishing universal ones, and many provisions are confidential.

Delivery structure changes what a contracted quantity even refers to. Under free-on-board terms, title, risk and shipping responsibility transfer at the loading terminal under the contract’s wording. Delivered structures place more shipping responsibility with the seller. The same annual quantity means a different set of obligations depending on which structure applies.

Actual exports are the only one of the four that is a measurement, and they sit at the end of a chain that can bind anywhere. Feed gas supply, pipeline access, power, plant availability, shipping allocation, buyer nominations and destination acceptance all constrain what moves. Boil-off gas has to be recovered, used as fuel, reliquefied or otherwise managed, so some of what enters the tanks does not leave as cargo.

Canadian evidence has to be dated because the situation changed recently. Natural Resources Canada’s LNG page was last modified in January 2025 and predates the country’s first export cargo. LNG Canada reported loading that cargo at Kitimat on 30 June 2025 and described initial two-train capacity as 14 million tonnes per annum. That event and that nameplate figure are operator statements: the first is a dated fact about one shipment, the second is a design rating rather than proof of annual output.

Two conversions are needed before any of these quantities can be compared, and both require information the headline number omits.

Units do not convert by inspection. LNG quantity may be stated as tonnes, as cubic metres of liquid, or as gas or energy equivalent, and conversions depend on composition, density, heating value, temperature and reference conditions. Gas liquefies near minus 160 degrees Celsius at around atmospheric pressure and occupies roughly one six-hundredth of its gaseous volume, which is why the unit chosen changes the apparent magnitude enormously.

Periods do not align. A licence term, a plant’s design year, a contract’s annual quantity and a month of shipments cover different windows, and comparing them without annualising on a common basis produces a ratio that means nothing.

Asked on the floor

What does an export licence actually authorise?
Exports up to an authorised quantity and term, subject to conditions. It does not guarantee feed gas, buyer performance, market margin, construction, or that anything is exported at all.
Is nameplate capacity what a plant produces?
No. It is a design figure. Ambient temperature, feed composition, driver and power source, outages and boil-off management all determine actual output.
Does take-or-pay guarantee cargoes move?
No. It can require a buyer to take and pay or compensate the seller. Parallel seller obligations and contractual excuses also apply, and payment does not create a shipment.
Can I convert tonnes of LNG to cubic metres of gas?
Only with composition, density, heating value, temperature and reference conditions. LNG quantity can be stated as tonnes, cubic metres of liquid, or gas or energy equivalent, and these are not interchangeable.

Sources

  1. Natural Resources Canada — Liquefied Natural Gas in Canada (January 2025)
  2. LNG Canada — First Cargo Puts Canada on the Map of LNG Exporting Nations (June 2025)
  3. Canada Energy Regulator — Filing Manual Guide Q: Export Authorizations
  4. Canada Energy Regulator — Oil and Gas Export Licence FAQs (2026)
  5. U.S. Securities and Exchange Commission — Centrica LNG sale and purchase agreement exhibit (March 2013)