Approved, financed, and built are three different things
A large energy project passes through a sequence of decisions made by different bodies under different tests, and each produces a document that can be mistaken for completion.
A large energy project passes through a sequence of decisions made by different bodies under different tests, and each produces a document that can be mistaken for completion. A regulator’s approval answers a statutory question and supplies no money. A financing commitment is a promise to advance funds under conditions. Construction is physical work. Operation is a further authorisation and a further set of tests. Reading any one of these as the others is the most common way a project’s status gets misreported, and the corpus records the gap at every stage.
Regulatory approval is permission to proceed against a defined test, not an endorsement of viability. Under the Canadian Energy Regulator’s framework a company must support a facilities application with evidence about corporate structure, financing methods, financial capacity and risks to construction and operation. That is application evidence submitted to a regulator. It is not a financing approval by the regulator, and the regulator does not supply funds.
Approvals are also plural and partial. A certificate is not every required authorisation, and a permit can carry conditions and remain exposed to compliance, judicial review, later variation and other required authorisations from other bodies. A federally regulated pipeline can still encounter provincial laws of general application, municipal requirements, environmental processes, land and water authorisations and emergency coordination. Approved by one body means approved by that body.
Different sectors formalise the staging differently, and nuclear is the clearest case because the stages are named. The Canadian Nuclear Safety Commission licences facilities through lifecycle stages, and a licence to construct does not authorise operation. An optional vendor design review provides early regulatory feedback: it does not certify a design, issue a licence, or bind the Commission. A policy announcement, a vendor review, a site-preparation licence, a construction licence, first concrete, fuel loading and commercial operation are seven distinct milestones, and Darlington’s construction licence contains regulatory hold points that gate progress within a single stage.
Authority to sell is separate again from authority to build. The Canada Energy Regulator issues gas export authorisations that address whether proposed exports meet the statutory test, along with the authorised term and quantity. An export licence is not a construction permit, not a financing commitment, and not an operating asset.
Financing has its own ladder, and its rungs are routinely collapsed. Facility commitment is not cash drawn. A reported project cost can include owner costs and financing items absent from a construction contract. Committed equity has to be funded on a schedule, and financing documents determine what counts as equity and when it must be provided — original development spending may count toward required equity only if the documents recognise it. Export Development Canada’s project-finance guidance places committed equity and key engineering, permitting and early-financing milestones before detailed lender diligence, which means a project with lender interest may be several steps from money.
Even completion is more than one event. During construction, project debt is commonly limited-recourse with sponsor or contractor support, and specified support releases only after tests and commercial operation. Commercial operation under a power purchase agreement can have a different definition from financing completion, so a plant can be operating for one contract and not yet complete for another.
Agreements between parties have the same problem. A memorandum is not an executed agreement; an executed agreement is not performance; and conditions precedent, effectiveness, payment and delivery are separate states. The Churchill Falls sequence shows the whole ladder in one file: a non-binding memorandum in 2024, a cooperation and implementation agreement signed on 17 August 2026, and forecast benefits that remain party estimates until the underlying formulas, projects and cash flows are observed.
Schedule is where the stages compound, because time between them is not free. A long build consumes capitalised interest, escalation and owner costs whether or not physical scope changes, so delay between an approval and a financial close raises the cost of the project that eventually gets built. A financing model has to schedule annual capital draws, escalation, contingency, capitalised interest, fees, owner costs and reserve funding against the construction programme rather than against a total.
Each stage also carries its own reversal risk, and the risks are not the same. An approval can be varied, judicially reviewed or conditioned. A financing commitment can lapse when conditions precedent are not met. A construction programme can be halted by an integrity finding or a supply failure. Treating a project as de-risked once it clears one gate assumes the earlier gates stay open, and they can close behind it.
The most reliable evidence is the one nobody publishes as a headline. Cash drawn, concrete placed, equipment installed, tests passed and product delivered are observations rather than intentions, and each has a record somewhere in a filing or a regulator’s decision. A status claim built from those is checkable; one built from announcements is a chronology of hopes.
Three habits keep the confusion alive, and each has a different remedy.
Announcements are written to sound terminal. The remedy is to ask which body decided what, under which authority, on what date, and what the next required decision is.
Aggregate figures mix stages. A pipeline of announced projects, a list of approved ones and a set under construction are three different populations, and adding them produces a capacity number that no year will deliver.
Regulatory language sounds like commercial language. Approved, committed, authorised, licensed and secured all appear in both vocabularies with different meanings, and the document that uses the word is the one that defines it.
Asked on the floor
- Doesn't a regulator's approval mean a project is going ahead?
- No. An approval addresses the regulator's statutory question and supplies no funds. Projects are approved and never built, and the approval remains valid while nothing happens.
- Is a construction licence an operating licence?
- No. Nuclear facilities are licensed through lifecycle stages, and a licence to construct does not authorise operation. Each stage is a separate decision on separate evidence.
- Is committed capital the same as money spent?
- No. Facility commitment is not cash drawn, and a reported project cost can include owner costs and financing items absent from any construction contract.
- Why does this keep going wrong in reporting?
- Because each stage produces a public document that reads like completion. An announcement, a permit, a signed agreement and a first shipment are all newsworthy, and only the last is evidence that the thing works.
Sources
- Canadian Nuclear Safety Commission — New reactor and power plant projects
- Canadian Nuclear Safety Commission — Licensing, regulation and public hearings
- Canadian Nuclear Safety Commission — Darlington New Nuclear Project
- Canada Energy Regulator — Regulation of Pipeline Traffic, Tolls and Tariffs
- Canada Energy Regulator — Filing Manual Guide P: Tolls and Tariffs
- Canada Energy Regulator — Filing Manual Guide Q: Export Authorizations
- Export Development Canada — Project finance